Risk scenario analysis describes a plausible sequence of events and tests its effect on a decision. Build a small number of internally consistent cases. For each one, record the initiating event, current conditions, response options, timing and consequences. A scenario can reveal which assumption deserves investigation before a team commits money or accepts a delay.

Model when the stock runs out

A maintenance business holds 180 replacement parts and normally uses 30 per day. A shipment may arrive in four or eight days. At average demand and with no partial delivery, stock covers six days. Four days leave 60 units on hand. Eight days create a shortfall of 60 units. Label when in the day the shipment becomes available and whether demand can be deferred. Those details matter when an order arrives near the coverage boundary.

During a busy week demand rises to 40 units a day. Over eight days the shortfall becomes 140 units. A second supplier can deliver 50 on day five. Under those assumptions, 90 units remain uncovered across the period. Ask maintenance which jobs are affected first and check whether the substitute is approved for every job. A volume estimate alone cannot identify which customers will wait.

Find the decision threshold

The purchasing manager could reserve stock at the second supplier, authorize substitution for one class of job or change planned maintenance dates. List what each response costs, who approves it and how late the choice can be made. Show the delivery delay or demand level at which the preferred response switches. Keep assumptions that move together in the same case, such as regional transport disruption affecting both suppliers.

Use the supply chain risk assessment to check common transport dependencies. Where a supplier reserve becomes a firm commitment, capture the owner and proof of availability in the risk treatment plan. Revisit the cases when actual demand, delivery dates or approved substitutes change.